RAISE THE ROOF!
Yes, it’s that time again!
Time to roll up our sleeves, hike up our overalls, open our hearts and lend a hand in another wonderful Habitat for Humanity project!
Beginning May 3rd
and for the seven weeks following, our parish and several churches belonging to
the
We need volunteers from our parish to work on this project, starting with this Saturday, May 3rd. Below is the schedule for the tasks on each given day. Please respond to me at ricklozano@mindspring.com if you can make it this Saturday, and also please list what other days you’d like to participate. We’ve always stepped up as a parish on these projects and I’m sure I can speak for everyone in saying that these projects have always been rewarding.
I look forward to hearing from you.
Regards,
Rick Lozano
· You must be at least 16 years of age to work on the build
· Please note that the first three days involve heavy work and some level of danger if you work on the roof.
·
We will meet at St. Martin at 7AM early on the day of each build and
carpool to the build site (leaving
·
***
|
Day 1- May 3 |
Clear Crawlspace and paint foundation Set floor joists Lay floor decking Sheath panels and run exterior walls Run interior walls Tie walls together; straighten and brace Install lower porch package |
|
Day 2- May 10 |
Prep and run trusses Deck roof Felt roof Install sub-fascia; barge rafters and drip edge Install windows and trim packages Interior framing – wind bracing, deadwood, attic stairs Set up for siding – corner boards, skirt board, drip cap and starter strip Build side porch and ramp |
|
Day 3 – May 17 |
Shingle roof Insulate walls and ceiling Continue siding and caulking Install underlayment in kitchen, dining room and bathroom Build side porch and ramp |
|
Day 4 – May 31 |
Interior painting Finish siding and caulking Exterior painting – siding, foundation, trim |
|
Day 5 – June 7 |
Interior painting Exterior painting Install baseboard, window sills and miscellaneous interior trim Install kitchen cabinets and countertops Begin soffit and fascia |
|
Day 6 – June 14 |
Interior painting Exterior painting Finish soffit and fascia Install porch railings |
|
Day 7 – June 21 |
Install doorknobs and bathroom hardware Clean house interior Complete miscellaneous items Touch up interior and exterior painting Rake and clear lot Landscape DEDICATE NEW HOME! |