RAISE THE ROOF!

 

Yes, it’s that time again!

Time to roll up our sleeves, hike up our overalls, open our hearts and lend a hand in another wonderful Habitat for Humanity project!

Beginning May 3rd and for the seven weeks following, our parish and several churches belonging to the Brookhaven Christian Ministries will work side by side to provide another deserving family a new home, a new start and a chance to live the American Dream.

We need volunteers from our parish to work on this project, starting with this Saturday, May 3rd. Below is the schedule for the tasks on each given day. Please respond to me at ricklozano@mindspring.com if you can make it this Saturday, and also please list what other days you’d like to participate. We’ve always stepped up as a parish on these projects and I’m sure I can speak for everyone in saying that these projects have always been rewarding.

I look forward to hearing from you.

Regards,

Rick Lozano

ricklozano@mindspring.com

 

Additional notes:

·        You must be at least 16 years of age to work on the build

·        Please note that the first three days involve heavy work and some level of danger if you work on the roof.

·        We will meet at St. Martin at 7AM early on the day of each build and carpool to the build site (leaving St. Martin at or around 7:30AM. I will have directions to the site and notes posted on the Parish Website.

·         ***St. Martin’s day to provide lunch for the volunteers is DAY 7, DEDICATION DAY!! This is a great opportunity for those of you who can’t or choose not to work on the build can contribute through your culinary skills, and also be on hand for the dedication. Words cannot describe the emotions shared by everyone when the keys are finally turned over to the homeowners. Even if you didn’t volunteer, this is a very special day and not one to be missed.

 

 

 

 

 

 

Habitat Build Schedule – Tasks by Day

Day 1- May 3

Clear Crawlspace and paint foundation

Set floor joists

Lay floor decking

Sheath panels and run exterior walls

Run interior walls

Tie walls together; straighten and brace

Install lower porch package

Day 2- May 10

Prep and run trusses

Deck roof

Felt roof

Install sub-fascia; barge rafters and drip edge

Install windows and trim packages

Interior framing – wind bracing, deadwood, attic stairs

Set up for siding – corner boards, skirt board, drip cap and starter strip

Build side porch and ramp

Day 3 – May 17

Shingle roof

Insulate walls and ceiling

Continue siding and caulking

Install underlayment in kitchen, dining room and bathroom

Build side porch and ramp

Day 4 – May 31

Interior painting

Finish siding and caulking

Exterior painting – siding, foundation, trim

Day 5 – June 7

Interior painting

Exterior painting

Install baseboard, window sills and miscellaneous interior trim

Install kitchen cabinets and countertops

Begin soffit and fascia

Day 6 – June 14

Interior painting

Exterior painting

Finish soffit and fascia

Install porch railings

Day 7 – June 21

Install doorknobs and bathroom hardware

Clean house interior

Complete miscellaneous items

Touch up interior and exterior painting

Rake and clear lot

Landscape

DEDICATE NEW HOME!